Show Barn Construction Photos
Click an image below to see a full-size version.
11/2/2021 - Triple C Construction begins digging foundations. These footings are substantial due to the size of the structure.
11/29/21 Form Building
1/10/22 Rebar installed
1/10/22 Construction of plints
1/28/22 Plint construction complete
2/1/22 Concrete being poured into forms.
2/1/2022 - Forms have been installed and footings have been poured with cement. Cure time should be between two and four weeks, following which the steel of the structure can begin to be erected.
2/4/2022 Forms have been removed from the footings and the concrete is curing.
2/10/22 Steel Arrives